-->

Production manufacturing solution

Translate

Section 3- Re-sequencing the schedule

  

We will add a sequence column to the left of the table:

If we do job B last, four out of the five jobs will be on time. The table was sorted into a different
sequence by entering the numbers 1 5 2 3 4 down the sequence column, and with the pointer in the sequence column, clicking on the 'sort ascending' icon.
Labels: Scheduling Excel Basic

Thanks for reading Section 3- Re-sequencing the schedule. Please share...!

0 Komentar untuk "Section 3- Re-sequencing the schedule"

Back To Top