Section 29 Multiple Work Centre - Pull Schedule

Multiple Work Centre - Pull Schedule

To examine pull scheduling logic further we have repeated the push schedule in Section 20, and compared it with a pull version of the same schedule. The pull schedule works backwards from the stop of the last job, and each job will be dependent on the next job on the work centre, and the next operation on the job.