Section 24 Calendar-based Repetitive Production Using Several Work Centers

Calendar-based Repetitive Production Using Several Work Centers

Here is the Section 21 schedule with several calendars assigned to the work centers and calendar calculations applied in three separate places:
    - first computations use the calendar for the subsequent operation to apply the lag period 
     and cease the prior operation.
    -second calculations add the operation duration to the start; the third calculations utilize          
    the start again, reuse Calc4 and Calc5, and add the lag duration; the subsequent operation 
      in column L then finds the outcome.