Section 17 Gantt Chart 3 - Units per Day

 For repetitive production, you may wish to show the number of units that can be produced in a day, rather than the number

of hours of a job that falls into each day. The Gantt chart in Section 16 can be extended to do this, by multiplying the hours

by the units per hour. Lets take a repetitive production schedule, as in Section 15, but with one work centre:


This report is useful as a production target to be issued at the beginning of a week, as it is easy to compare actual performance
against it. In setting a production target for a day, it takes into account:
- calendar hours each day (production is lower on a Friday)
- each product runs at a different speed
- the set-up time depends on the previous product
Labels: Scheduling Excel Basic